A construction site needs power before the mains arrives and often after it is switched off for the day. Generators solve it and create three problems: fuel, noise and idle running.
What the site draws
| Load | Draw | Duty |
|---|---|---|
| Site office and welfare | 1–5 kW | Working hours |
| Hand tools and chargers | 1–3 kW | Intermittent peaks |
| Lighting towers | 0.4–1.3 kW | Night |
| Hoist or lift | 5–20 kW | Short, high current |
How to size the pack
1. Base load. Welfare units and offices run continuously; that is the kWh that matters.
2. Peaks. A hoist start is seconds, not hours. The battery covers base load and the generator starts for the peak.
3. Night shift. Lighting plus heating or cooling overnight is often the largest single block.
Why batteries are replacing idling generators
A generator sized for a hoist runs at 5% load the rest of the day, burning fuel to make noise. A battery pack covers the base load and lets a smaller generator start only when the hoist needs it — the same logic as a hybrid.
Cold sites
Winter sites are where sodium’s discharge window matters: a pack in an unheated container still works at −20 °C, while a lead-acid bank loses a third of its capacity and a lithium pack may refuse to charge without heating.
Where it does not pay
A permanent site supply. If the generator only covers outages, a battery changes little.
A short project. Under about three months, hire costs beat any capital purchase.
Questions buyers ask
Can it replace the generator entirely?
For base load and lighting, often yes. For hoists and heavy tools, no — the peak is too large.
How is it moved between sites?
In a container or on a towable frame. Weight and lifting points are part of the specification.
Does it need a permit?
Usually less than a generator: no fuel storage, no emissions. Noise permits are the usual driver.
Can it be charged from site power?
Yes, and that is the normal arrangement once a supply exists.