An event site cannot run a generator next to a stage microphone, and a film set cannot put one in frame. Battery packs solve both, if they can deliver the peak a lighting rig asks for.
What a rig draws
| Load | Draw | Duration |
|---|---|---|
| LED stage wash (x8) | 1–2 kW | Hours |
| Moving heads (x8) | 2–4 kW | Hours |
| Audio rig | 0.5–3 kW | Peaks on bass |
| Film lighting, HMI | 2–6 kW | Short takes |
Peak current, not energy, sizes the inverter; energy sizes the pack. The two are often confused on site, which is why rigs run out of power in the middle of a set.
Silence is the product
No fumes, no noise, no fuel run. For indoor venues and residential locations the alternative is a long cable run or a permit argument — which is why the cost is easier to justify than it looks.
Charging between shows
A pack that accepts a fast partial charge turns around between rehearsals. Sodium’s charge acceptance suits that duty; the charger and site supply become the limiting factors.
Where it does not pay
Large outdoor stages still use generators for a reason — the energy requirement is beyond what a portable pack can carry. Battery rigs fit mid-size events, film and indoor work.