Build the battery management system (BMS) around your pack
Set the cell chemistry, the string count and the current — the protection thresholds, the pack voltage and the closest standard board are updated as you go. Send the finished configuration and we quote against it.
Thresholds follow the chemistry. Final values are set from the cell datasheet and confirmed in the brief.
Starting current sets the peak rating, not the continuous one.
Simultaneous starts add up — the pack sees the sum of the surges.
What the motor draws
Motor powerkW
Regenerative braking
Drive current at this voltage is calculated below.
Send the configuration
You have already built the specification — we only need somewhere to reply. One working day for thresholds, drawing and price.
Threshold sheet for your cells
Board drawing and connector list
Sample lead time and tooling cost
Standard boards we already build
Start from one of these when the configuration is close; otherwise we design from the brief. Sodium-ion boards are built to your thresholds — none of the standard boards above is sodium-specific.
01 · BriefYour configuration arrives with thresholds, current and communication already set.
02 · Threshold sheetWe return the protection table for your exact cells — over-charge, release, delay, balance start.
03 · SampleBoard, harness and enclosure built to the sheet; typically 10–15 working days.
04 · ProductionBatch testing against the same sheet, with the test record shipped alongside.
Three questions behind the BMS selection
Why does a pack refuse to charge at −5 °C?
Because the charge cut-off temperature is a cell property, not a board setting: one 220 Ah prismatic cell permits no charging at or below −10 °C and limits the rate to 0.20C between −30 °C and 0 °C.
Discharge remains allowed to −30 °C on the same cell — only charging is restricted
0.20C means roughly five hours for a full charge in that window
A heater or a warm-up schedule is the system answer, not a lower threshold
Why is a pre-charge circuit not optional on an inverter load?
An inverter presents a large capacitance at switch-on, which looks like a short to the pack for a few milliseconds; the pre-charge resistor limits that inrush so the contactor does not weld.
Direct-on-line motor starts draw up to six times running current — peak rating, not continuous, decides the contactor
Two motors starting together multiply the surge
Insulation monitoring and an interlock loop are separate from the pre-charge function
We use one first-party cookie to remember your language and consent choices. No advertising or cross-site tracking is loaded unless you accept analytics. Read the privacy notice.